Project Status and FAQs for the San Martin Blvd. Bridge Replacement Study
Project Status
A Preferred Alternative has been selected based on consideration of potential environmental impacts, social and physical impacts, engineering issues and public input received throughout the study. This alternative was presented at the virtual public meeting held on Nov. 18, 2021.
The PD&E study was completed in April 2022. The design phase began in Spring 2023 and is underway. Two public meetings are planned during the design phase.
San Martin Boulevard Bridge Tentative Project Timeline
Milestone | Date |
Project Development and Environment (PD&E) Preferred Alternative presented at Virtual Project Information Meeting | November 2021 |
PD&E Study complete | April 2022 |
Begin Design Phase | May 2023 |
Project Information Meeting # 1 (during design phase) | Summer 2024 |
Project Information Meeting # 2 (prior to construction) | Summer 2026 |
Anticipated completion of Design phase | Fall 2025 |
Anticipated start of Construction phase | Late 2026 |
Why is the project needed?
Replacement of the San Martin Boulevard Bridge is needed to correct the deficiencies of the existing bridge. The bridge was constructed in 1962 and is nearing the end of its service life. The existing bridge does not meet current design standards and Americans with Disabilities Act (ADA) requirements. This study was undertaken in accordance with the federal National Environmental Policy Act (NEPA) process. Compliance with the NEPA process allows the County to remain eligible for federal funding.