Project Status and FAQs for the San Martin Blvd. Bridge Replacement Study

San Martin Blvd over Riviera Bay bridge replacement area

Project Status

A Preferred Alternative has been selected based on consideration of potential environmental impacts, social and physical impacts, engineering issues and public input received throughout the study. This alternative was presented at the virtual public meeting held on Nov. 18, 2021.

The PD&E study was completed in April 2022. The design phase began in Spring 2023 and is underway. Two public meetings are planned during the design phase. 

San Martin Boulevard Bridge Tentative Project Timeline

Milestone Date
Project Development and Environment (PD&E) Preferred Alternative presented at Virtual Project Information Meeting November 2021
PD&E Study complete April 2022
Begin Design Phase May 2023
Project Information Meeting # 1 (during design phase) Summer 2024
Project Information Meeting # 2 (prior to construction) Summer 2026
Anticipated completion of Design phase Fall 2025
Anticipated start of Construction phase Late 2026

Why is the project needed?


Replacement of the San Martin Boulevard Bridge is needed to correct the deficiencies of the existing bridge. The bridge was constructed in 1962 and is nearing the end of its service life. The existing bridge does not meet current design standards and Americans with Disabilities Act (ADA) requirements. This study was undertaken in accordance with the federal National Environmental Policy Act (NEPA) process. Compliance with the NEPA process allows the County to remain eligible for federal funding.