Grant Funds and Sources /
Use of Project Funds

Figure 2

Figure 2 (Download PDF)

This project requests $19,156,129 in TIGER VII funding to complete the two Pinellas Trail Loop gaps, a North Gap and a South Gap. Figure 2 portrays the Loop gaps in detail. Table 1 shows the overall project cost and funding, by source. A budget is available in Appendix A.

As the remaining segments of the Pinellas Trail Loop will be constructed using a design-build contract, a more detailed budget will be developed during project design, and is therefore not yet available. Alternative alignments and crossings are available, if necessary, to compensate for any unanticipated expenses.

Table 1 - Project Funding
Cost
Phase 1, North Gap (Enterprise Rd. to Brighthouse Field) $5,589,066
Phase 2, North Gap (Chesnut Park to Enterprise Rd. $9,252,860
Phase 3, South Gap (Belleair Rd. to Ulmerton Rd.) $4,560,255
Phase 4, South Gap (Ulmerton Rd. to San Martin and Miscellaneous*) $11,681,049
Total $31,083,230
* Includes intersections/signalization, design & survey, mobilization, MOT, geotech and testing, unforeseen additional items, contingency, as-builts / project close out
Local Match
Pinellas Trail Extension Program, North Gap $3,077,100
Pinellas/Duke Energy Trail Extension, North Gap $4,912,000
N.E. Coachman Road at Coachman Road Intersection Improvement, North Gap $400,000
Old Coachman Road over Alligator Creek Bridge Replacement, North Gap $300,000
Intersection Improvements, North Gap** $1,055,200
San Martin Blvd. over Riviera Bay Bridge Replacement, South Gap*** $600,000
Intersection Improvements, South Gap** $1,582,800
Total $11,927,100
** Intersection improvements include as-needed crossing improvements, 40% for North Gap and 60% for South Gap
*** San Martin Bridge funds allocated for this project are separate from the funds set aside for a federal grant match for the bridge construction
Funding Breakdown
Total Cost $31,083,230
Local Match $11,927,100
Local Match (%) 38.37%
TIGER Grant Request $19,156,130
TIGER Grant Request (%) 61.63%
Note: The pre-application had a project total of $32,000,000, including a TIGER request of $20,000,000 and a local match of $12,000,000.