Public Works CIP Project Update
Last updated June 2020
Anclote Road Roadway and Stormwater Improvements
Project ID# 003897A
Project Location
Anclote Road and Alt. U.S. 19 N.
Project Overview
This project includes preliminary engineering to assess typical section options for Anclote Road, recommend limits for final design and evaluate options for drainage improvements. The study will also assess drainage improvements to resolve flooding on Center Avenue between Anclote Road and Fulton Street and improve stormwater collection along Savannah Avenue between Anclote Road and Brady Road.
Project Schedule
- Design Start: Fall 2018
- Design End: Fall 2023
- Construction Start: Winter 2024
- Construction End: Fall 2025
This project is funded through the Penny for Pinellas program.
Project Contact
Victoria Preston -- Project Manager
Public Works, Stormwater Planning & Engineering
14 S. Ft. Harrison Ave., 4th Floor
Clearwater, FL 33756
(727) 464-3687
SWProjects@pinellascounty.org