  Frequently Asked Questions


The following is a list of questions and answers that are commonly asked. The answers pertain to the unincorporated area of Pinellas County. Should you live in one of the communities that are currently under contract with this department they might not apply.


1. Do I need a permit for a fence?
You must comply with any zoning regulations, but a building permit is not required in the unincorporated area of the county. You may contact a zoning representative at 464-3888.

2. Must I place street numbers on my house or business?
Yes, these are required under county ordinance 87-52. They must be over the front entrance and 3" minimum in height. If the business is located on U.S. 19 the numbers must be 5" in height.

3. Do I need a permit for a driveway?
You will need to obtain a county Right-of Way Utilization Permit from the Public Works Department (464-2370) however, a building permit is not required for new or extension of a driveway. Also you must comply with all zoning and environmental regulations. You can contact a zoning as well as an environmental representative at 464-3888.

4. How long is a permit valid?
A permit is valid for six months from the date of issuance, or from the last approved inspection date. If the project is dormant for six months then the permit is expired. A permit may be extended only by the Building Official with a written request.

5. At what stage of construction can I get my power turned on?
Power will not be released under most circumstances until the building has received all required inspections and all fees due are paid. We do issue what is known as temporary power for specific items that require testing prior to occupancy.

6. When are plans required and what do I need to show on the plans?
Plans are normally required for most construction projects. For a list of requirements that need to be shown on plans go to 1. residential plans or 2. commercial plans.

7. How many layers of roofing can be installed before I have to remove the old roofing to install new roofing?
You must follow the roofing material manufacturers specification. Under most instances a second layer of roofing shingles cannot be appied over the original shingles.

8. Where can I obtain the code books that are enforced in Pinellas County?
All of the Florida Building Codes can be obtained through BOAF Market Place or through the State of Florida. The National electrical code and the N.F.P.A. codes can be obtained through The National Fire Protection Association. You also may find them in your local library, or at some of the larger book stores.

9. What work can I do as an owner?
As the owner of a one or two family dwelling you my act as your own contractor and do the work yourself, provided that the home is for your own use, it is not for sale or lease. You must also be doing the work yourself, or providing direct on site supervision. If you are the owner of a commercial property you are required to hire a contractor for any work that requires a permit and inspection.

10. As the owner of a single family home, can I hire people to help me or must I use licensed contractors?
As the owner you may hire laborers to help you in the construction. However you must supervise any of the laborers you hire. At the time of permitting you will need to turn in a Homeowner Affidavit. You must also comply with Florida Statues with regard to workers compensation and federal taxes. You can enter into a contract for the different categories of work (electrical, plumbing, mechanical, etc.) as long as the person you hire is a licensed contractor.

11. Are plans for a single family home required to be sealed by and architect or engineer?
Plans must be signed and sealed by a Florida registered architect or engineer, or they must comply with a hurricane resistant construction design manual, known as SSTD 10-99 and their accompanying worksheets.

 