|
Environmental Home Page
2005
Sand Key Project
Sand Key
Beach Home
What's New? 
Funding
History
Environmental Impacts
FAQ's
Why Renourish?
Maps

512 S. Ft. Harrison Avenue
Clearwater, FL 33756
Phone: (727) 464-4761
Fax: (727) 464-3174
Web Site
© 2008 Pinellas County
All rights reserved
|
|
View a slide
show of the dredging operations
to mobilize for beach Renourishment.
The borrow site, or the area from which sand
will be dredged, is the Egmont Shoal. This
is the large sand bar offshore of the entrance
to Tampa Bay, and to the north of Egmont Key. The
shoal will be dredged with a clamshell or bucket
dredge, the “Atlantic”. A bucket
dredge is essentially a floating barge with
a bottom opening bucket at the end of a crane. To
excavate material, the bucket is lowered into
the sediment, closed, then raised to the surface. The
closed bucket is then positioned over a scow,
or sand barge, and opened, placing the dredged
material into the scow. |
|
The
bucket dredge “Atlantic” of
Norfolk Dredging Company that will
be used on the project.
|

Bucket dredge loading
scow.
|
|
The loaded scows will be pushed to the
beach project area with tugboats. Once
offshore of the beach, the scows will be
hooked up to an unloader, the “Vicksburg”,
that will pump the sand through a submerged
pipeline to the beach. The
project will place nearly 2 million cubic yards
of sand. Approximately
800 scow loads will be transported from
Egmont Shoals to the beach project area.
|
|

Scow
being pushed by a tug.
|

Unloader "Vicksburg" prepares
to unload a scow.
|
|
The Egmont Shoal
is located about 3 miles due west of
Ft. DeSoto Park. This sand shoal
has been dredged numerous times in the
past to place high quality beach sand
on the beaches of Pinellas County. The
sand meets stringent state environmental
criteria. This borrow area is located
far enough offshore that dredging of
the shoal will not affect waves that
reach the shore, and will not cause erosion
of the shoreline. There are no reef or
hardbottom communities in or near this
borrow area that will be impacted by
dredging activity.

1990
Sand Key Phase II Nourishment.
|
The above map identifies
the Sand Key project area in relation to the borrow
area.
|
|
Construction equipment on the
beach. During construction,
a submerged pipeline will run from the
unloader to a landing point on the beach.
Upon arrival of a scow, the scow will
be unloaded and sand will be pumped in
a slurry of sand and water to the beach.
Then, beach construction will proceed
to the north by adding additional pipeline
along the beach. This pipeline
will remain on the beach during the construction
of each shoreline section. Next,
the pipeline will be “flipped” and
nourishment will proceed to the south.
Once the entire beach section as been
nourished, the landing point and pipeline
will be demobilized and relocated to
construct the next section. During construction,
temporary sand ramps will be maintained
over the pipeline at regular intervals
to provide safe public access to the Gulf and newly widened beach.
|
|

Renourishment
construction at Upham Beach, July 2004.
|

Pipeline on
the beach during July 2004, Long Key renourishment
at Upham Beach.
|
|

Above
and Right:
Sand being pumped ashore at Upham Beach,
July 2004.
|
 |
|
Bulldozers
will redistribute the sand that is pumped
to the beach to create a smooth wide
beach. Dozers
and other construction equipment will be
operated around the clock, creating noise
from engines and safety backup alarms,
and using lights from dusk until dawn.
The small, active construction area typically
will move along in 7 or 8 days. Approximately
100 feet of beach will be constructed per
day. The
contractors will be working around the
clock. Safety backup alarms are exempt
from all local noise ordinances.
The beach areas in the
immediate vicinity of the active construction
will be closed. Construction equipment
and the operating pipeline pose a safety
hazard to beach goers. A powerful
fountain of sand will be discharged from
the pipeline. Please obey all posted
signs and stay out of the construction
area.
View
a slide show of the tentative plan for
construction equipment on the beach.
|
|
Type
of sand. Expect the
nourished sand to appear darker in color
than the sand in place previously. Nourished
beaches usually start out a slightly darker
shade than the existing sand, because the
sand was taken from underwater. Once
the sand is exposed to the sun, it will
lighten. The sand may also be coarser
(larger grains) than the existing sand. The
sand that will be placed on the project has met all state sand requirements
for color, content, and size.
During the 1998-99 Sand
Key Project, a large volume of fist-sized
rocks was pumped onto the beach. An
annual rock removal program was necessary
in which the top 3 feet of beach sand was
sifted to remove the rock. Every
effort has been made to avoid placing rock
on the beach during the 2005 project. A
detailed rock removal plan has been developed
in case the contractor discovers rock in
the borrow area. The first million cubic yards of sand was screened with a large cage, or screening basket, placed at the pipeline discharge. Due to the high quality of sand so far, the screen is no longer required on the discharge pipe, but it will be kept on-site. The
construction contract specifically states
that rocks will not placed on the beach
during this project.
|

Annual
rock removal program by tilling the top
three feet of sand.
|
|

Large cage, or screening
basket, will be used to trap rocks and
large material.
|
|

The use of a screening
basket will trap material preventing
it from being placed on the beach.
|
|
Beach
width. The
beach will be constructed abnormally
wide because it is well known that the
beach will equilibrate soon after construction. This
means that the wide beach that is constructed
by the bulldozers will start to narrow
immediately. The
natural wave action will smooth the beach
to a gentler slope, thereby causing the
beach width to narrow. This process
does not involve a loss of sand from the
beach, rather a redistribution of sand
to the nearshore area and to the sand bar. Like
the existing beach, eventually about 2/3
of the new material will be underwater,
acting like the foundation of a house supporting
the dry beach. Although it will appear
that the beach is rapidly eroding after
nourishment, this is the normal process
in which the beach transforms from a constructed,
designed beach to a natural beach form.
|
|

Beach
equilibration after nourishment.
|
|
Breakwaters. In
the past, the U.S. Army Corps of Engineers
considered installing breakwaters at various
locations along Sand Key. After studying
of the success of the nourishment project,
the Corps has decided against breakwater
installation. This letter from
the Corps to Pinellas County describes
the Corps’ position on
breakwaters for Sand Key.
|
Top
of Page |
|